Published 5 May 2023Great news! We are pleased to inform you about the progress of our new terminal – Pier 5. The piling work has been completed, with a total of more than 350 piles driven into the ground ensuring the terminal remains in place. In addition, the foundation for our office has also been completed, and we have begun installing the drains.
View from Above:
Now, we are busy preparing for the construction of the warehouse. The rebar work for the concrete foundation has begun, and we are happy to report that everything is proceeding according to plan. Our new warehouse will cover an area of 25,000 square meters and is designed to meet the highest industry standards.
A foundation will be made in the coming weeks, after which the steel constructor can start building the warehouse.